NSW CDC Fire Documents: Design to Occupation

Use this phased NSW Fire CDC document checklist from design and system endorsement through construction, fire certification and occupation.

Fire-services drawings, inspection records and completion documents arranged by project stage

Fire documents are easier to control when they are organised by project stage. A single folder labelled “certificates” hides who produced each document, what it proves and when it must be accepted.

Stage 1: before CDC determination

Start with the information needed to define the compliance problem:

  • current architectural plans and proposed scope;
  • existing and proposed use and NCC classification;
  • rise in storeys, effective height, areas and compartments;
  • existing approvals, schedules and Performance Solutions;
  • water-pressure and flow information;
  • proposed occupancy, storage and special hazards; and
  • existing fire-system condition and capacity where retained.

The design package may then include system plans, specifications, calculations, schematics, passive-fire details, interface information and required practitioner endorsements.

If a fire Performance Solution is proposed, include the performance-based design brief, stakeholder consultation and final report process. Read when a NSW CDC needs a fire engineer.

Stage 2: when the CDC is issued

The issued CDC defines the approved work and conditions. The certifier also issues the applicable fire safety schedule, identifying essential and critical measures and their minimum performance standards.

Review the schedule immediately against the approved drawings and reports. Confirm that:

  • system names and performance standards are correct;
  • existing, altered and new measures are captured;
  • Performance Solution requirements are reflected;
  • the schedule covers the whole building where required; and
  • all approved document revisions are identified consistently.

Do not wait until occupation to resolve an obvious mismatch.

Stage 3: during construction

Maintain a controlled register of approved drawings, endorsed system plans, lawful variations and site instructions. For each fire measure, collect:

  • inspections and test results;
  • commissioning data;
  • product and tested-system evidence;
  • installation certificates within the issuer’s competence;
  • photographs where they support concealed-work records;
  • defects and close-out evidence; and
  • as-built plans and schematics.

Changes must be coordinated. Moving a wall can change sprinkler spacing and egress; changing a ceiling can affect detectors, warning devices and emergency lighting; adding penetrations can compromise fire separation.

Stage 4: completion and occupation

The owner arranges the fire safety certificate for applicable completed work. The principal certifier assesses the occupation-certificate application using the required regulatory and project-specific evidence.

Fire and Rescue NSW may have separate consultation, lodgement or pre-occupation processes depending on building class, relevant fire safety systems and Performance Solutions. Confirm the current pathway rather than relying on a previous project’s checklist.

Use CDC inspections and occupation certificates to plan the construction-stage sequence.

Stage 5: handover and ongoing operation

Provide the building owner or manager with:

  1. current fire safety schedule;
  2. fire safety certificate and occupation records;
  3. approved and as-built drawings;
  4. Performance Solution reports and management requirements;
  5. commissioning and baseline information;
  6. product and system documentation;
  7. maintenance contracts and logbooks; and
  8. the next annual and supplementary statement dates.

From 13 February 2026, NSW AS 1851-2012 obligations apply to covered essential measures in Class 1b and Class 2–9 buildings. Good handover prevents new owners from beginning that process with missing baseline data.

Use one document register

Track document name, revision, issuer, statutory purpose, approval status, related measure and storage location. That register should follow the project from design through occupation.

NEPA prepares and coordinates fire-services design information for Fire CDC projects. For a pre-lodgement package, use our CDC application documents checklist or contact us.

Common questions

Frequently asked questions

What fire documents are needed before a NSW CDC is issued?

Depending on the project, the package may include BCA/NCC assessment, coordinated system plans and specifications, required endorsements, Performance Solution documents, consultation records and technical inputs for the fire safety schedule.

Which NCC applies to a NSW CDC lodged in 2026?

Building Commission NSW states that CDC applications lodged on or after 29 July 2025 are assessed against NCC 2022 Amendment 2. NSW plans to adopt NCC 2025 on 1 May 2027.

What fire documents are needed for occupation?

The principal certifier may require the fire safety certificate, commissioning and test records, as-built information, practitioner or installer evidence, approved variations and other documents specific to the project.

Does occupation end the fire-document process?

No. Handover should establish the maintenance records, current schedule and information needed for future annual or supplementary fire safety statements.

Official sources

This article provides general information for NSW projects. Planning, certification and fire-safety requirements depend on the site, building classification, proposed use, scope and applicable law. Confirm the requirements for your project with the registered certifier, council and appropriately qualified practitioners.