NSW Fire Safety Schedule: CDC Guide
Understand what a NSW fire safety schedule lists, who issues it with a CDC, and how it controls completion certificates and ongoing compliance.
The fire safety schedule is one of the most important documents in a building’s compliance history. When it is accurate, designers, installers, assessors and owners can work from the same list of measures and standards. When it is vague or inconsistent, the problems can remain for years.
What the schedule does
A fire safety schedule identifies the essential and critical fire safety measures that apply to the building and the minimum performance standard for each. It should address the building as a whole, not only the tenancy or area being altered.
Measures can include active systems, passive construction and other safety provisions. The actual list depends on the building and approval; a generic list copied from another project is not appropriate.
When a schedule is issued
A schedule can be issued with a complying development certificate or construction certificate for applicable building work, and in other prescribed circumstances such as certain changes of use or fire-safety orders.
For a CDC, the registered certifier or council issues the statutory schedule. Fire-services designers, BCA consultants and other practitioners supply the technical information needed to identify measures and performance standards accurately.
Since 1 August 2023, NSW has required new schedules to use the government template. Rules for corrected, reissued or replacement schedules depend on the circumstances, so use the current NSW guidance.
Three documents people confuse
Fire safety schedule
The approval-stage control document. It says what measures apply and what minimum standard each must achieve.
Fire safety certificate
A completion-stage document issued by or on behalf of the owner after applicable new work. It confirms that the scheduled measures have been installed and checked by properly qualified people and are capable of performing to the scheduled standard.
Annual fire safety statement
An ongoing document issued each year by or on behalf of the owner of an existing building, supported by assessment from appropriately accredited practitioners.
Read the detailed fire safety certificate vs occupation certificate guide and annual fire safety statement guide.
Why accuracy matters at CDC stage
The schedule follows the building into occupation and maintenance. Common problems include:
- omitted measures;
- measures listed under vague or wrong names;
- performance standards that do not match the approved design;
- inconsistent schedules across staged approvals;
- a schedule that considers only the altered tenancy; and
- Performance Solution requirements that are not captured clearly.
These issues can delay a fire safety certificate, complicate annual statements and make maintenance scopes uncertain.
How the project team should coordinate it
Before the CDC is issued:
- confirm the building classification and whole-building fire strategy;
- reconcile existing schedules and approval records;
- identify new, altered and retained measures;
- state the applicable design and performance basis clearly;
- coordinate Performance Solution requirements; and
- review the issued schedule against the approved documents.
If an error is found, raise it with the certifier or council promptly. Do not wait until occupation or the first annual assessment.
Missing or incorrect schedules in existing buildings
NSW legislation provides pathways for a council to reissue a schedule where it has been lost or destroyed or where specified errors or omissions exist. The process requires evidence and council involvement; an owner or contractor cannot simply create a replacement and treat it as statutory.
Use our common fire safety documentation failures guide to plan a records recovery exercise. For coordinated design inputs on a new project, see NEPA’s Fire CDC service or contact us.
Common questions
Frequently asked questions
Is a fire safety schedule required for a CDC?
A fire safety schedule is issued with a CDC for applicable building work or change of use under the NSW regulatory framework. The certifier determines the measures and standards relevant to the building.
Who prepares or issues the fire safety schedule?
The statutory schedule is issued by the council, registered certifier or other relevant authority for the applicable pathway. Designers and practitioners provide technical information that informs it.
What does a fire safety schedule contain?
It identifies the building's essential and critical fire safety measures and states the minimum performance standard for each measure. It should be tailored to the whole building and approved design.
Can an owner edit an incorrect schedule?
No. Owners should not informally add, remove or change scheduled measures. NSW provides processes for councils to correct, reissue or replace schedules in specified circumstances.
Official sources
- NSW Planning — Fire safety certification
- NSW Government — Fire Safety Schedule template
- NSW legislation — Development Certification and Fire Safety Regulation 2021
This article provides general information for NSW projects. Planning, certification and fire-safety requirements depend on the site, building classification, proposed use, scope and applicable law. Confirm the requirements for your project with the registered certifier, council and appropriately qualified practitioners.